// PROJECTS

// PROJECTS

  • Builder: John Holland / NWPA
  • Value: $1.1m
  • Description: Installation of approx. 250T of steel for the main structural package.
  • Builder: John Holland
  • Value: $1.3m
  • Description: Installation of all the architectural cladding on the precast U- trofs.
  • Installation of all the stainless-steel balustrading through both stations and station signage.
  • Builder: Built
  • Value: $1.7m
  • Description: Installation of approx. 220T of steel for the main structural steel package.
  • Builder: Hansen Yuncken
  • Value: $550K
  • Description: Carpentry package installing doors, windows, hoardings and security screens.
  • Builder: SEPA – Laing O’Rourke and Metro Trains
  • Value: $1.66m
  • Installation of approx. 330T of steel for the main structural package.
  • Including 2 x lift shafts, main canopy, stairs and canopies
  • Builder: Downer
  • Value: $1.4m
  • Description: Structural package and delivery on cladding package.
  • Buider: BMD
  • Value: $250k
  • Description: Installation of all the cladding and fall protection along the surf coast overpass.
  • Builder: Kane Constructions
  • Value: $750k
  • Description: Installation of approx. 150T of steel for the main structural package. Warehouse and office space.
  • Client: Metro Trains
  • Value: $3.12m
  • Description: Installation of structural and metals works packages.
  • Installed concrete tilt panels.
  • Construct and erect ceiling frames and walls.
  • Builder: Built
  • Value: $750k
  • Description: Installation of approx. 200T of steel for HUB and Paint shed.